JSC Cryogenmash has signed a contract with Chongqing Endurance Industry Stock Co. to supply equipment for a liquefied natural gas plant with a 5 ton per hour capacity. The company will design, manufacture and supply the equipment before the end of 2011 and will also provide a range of services and training.
In the past four years, Cryogenmash has supplied more than five modular sets of LNG equipment to China, and four sets are slated for delivery in 2011. Previously, plants constructed with Cryogenmash’s equipment could produce 1.5 and 3 tons per hour. The new contract represents a move toward larger production capacities.
Cryogenmash is a Russian company and a major supplier of air separation technologies and equipment.